Augusta Bottom Road Bridge

The project involves the replacement of a deficient steel girder bridge on Augusta Bottom Road over a tributary to the Missouri River, located 0.5 miles east of Emke Road. Proposed improvements include:

  • New widener structure to provide for 12-foot lanes and 4-foot shoulders.
  • Realignment to allow old bridge to remain in place while new structure is constructed.

The project is funded by St. Charles County’s ½-cent Transportation Sales Tax and with Federal Highway Administration (FHWA) Surface Transportation Program-Suballocated (STP-S) funding. The project is estimated to cost approximately $730,000.

Contact Chris Bostic, Engineering Design Manager, at 636-949-7305 or cbostic@sccmo.org, with questions about the project. 

Current Phase

This project was recently recommended for funding and is listed on St. Charles County’s Transportation Improvement Plan (TIP) 2022-2024. Design began early in 2022. Construction is scheduled for 2024. The consultant has finished field surveys and just submitted Conceptual Plans for review.

Updated 4/26/22

Project Location Map